Recreating Recreation Timeline

RecreatRec_Approved

Recreating Recreation Project Timeline


Community Center Plans Date
Award contract to architect November 2016
Out for bids March 2018
Construction starts  June 2018
Construction complete March 2020
Other Recreating Recreation Projects                                                                      Start Date
Skate Park 2017 - Completed
Splash Pad 2017 - Completed
Farmers Market Pavilion/Ice Rink  2017 - Completed
Neighborhood Parks Projects  To be bid in groups, with first projects starting in 2017
Paddle Landings/Launches Temporary facilities 2017, permanent facilities 2018 (North Clinton River Park, Rotary Park) - Completed
Dog Park  2019 - Completed
Delia Park to Nature Center Trail  2019